Niagara College PM-Lite

PM-Lite Deliverables

The following deliverables are required for projects following the PM-Lite process

https://niagaracollege.teamdynamix.com/TDPortal/Images/Viewer?fileName=375c6ea6-d3d8-4a3b-a04f-1c24f3a908b9.PNG

Red (*) - Documented in TeamDynamix

TeamDynamix Deliverables

IT Initiatives identified as PM-Lite will be tracked using Team Dynamix (TDX). The following information will be tracked within TeamDynamix and kept up-to-date by the Project Coordinator and project team.

  • Basic project information from the Project Charter
  • Stakeholder list
  • Team Contact list
  • Project Register
    • Issues, Action Items, Defects, Project Changes
  • Risk Register 
  • Project Schedule
    • Waterfall or Agile
  • Weekly projects status updates outlining accomplishments, next steps and issues/concerns
  • Project binder will be used to store the following project related documents
    • Project Charter
    • Requirements Specification
    • Touchpoint meeting results
    • Any other project communications
    • User Acceptance Summary
    • Lessons Learned meeting results
    • Project Close Report
    • Additional documents that need to be shared with project team

PM-Lite Templates

The table identifies which project templates are required for projects identified as PM-Lite.

PM Stage

Deliverable

Format

Sign Off?

Request

Project Request Form

via TeamDynamix - Client portal

----

Project Scorecard

Excel

----

Define

Project Charter-Lite

Word

YES

by Sponsor

Stakeholder List

TeamDynamix - Stakeholder tab

---

 

NEW Set up Project Teams Site 

Named as: PRJYY-XXX <Project name>

all stakeholders should be added to it and also all communication should be done through the posts as opposed to email

MS Teams ---

Plan

Project Schedule

TeamDynamix - PM-Lite Plan

YES

by Sponsor

Requirements specification

Word

YES

by business owner

Execute

User Acceptance Summary

Word

YES

by business owner

Monitor & Control

Meeting Agenda/Results

Word

----

Touchpoint Meeting Agenda

-       Weekly

Word

----

Project Status Report

-       Weekly

-       Send to project team, project sponsor and stakeholders (as required)

TeamDynamix - Update Status

----

Project Change Log

TeamDynamix - Issues

----

Project Register Issues

·         Assumptions

·         Decisions

·         Defects

·         Action Items

TeamDynamix - Issues

----

Risk Register

Created in PLAN stage and then reviewed by team monthly as part of the team touch point meeting

TeamDynamix - Risk Register

----

Close-out

Lessons Learned Meeting 

(To be facilitated by the PPO)

Word

----

Project Close Report-Lite

Word

YES

by Sponsor


Details

Article ID: 79183
Created
Mon 5/27/19 2:06 PM
Modified
Wed 5/17/23 9:20 AM